Total Movements moves Flash Drum to India

0

Total Movements, member to the Worldwide Project Consortium (WWPC) in India, moved a 311 ton weighting Water Flash Drum to one of the largest petroleum refineries in India – a task that demanded more than just logistics.

It required resilience, precision, and the collective spirit of everyone involved.

A spokesperson for the project team explained: “From the supplier’s factory to the refinery foundation, this drum travelled by road, by barge, and through challenging terrain.

Our scope covered: Road movement to the nearest jetty; Rolling the drum safely onto a barge; Coastal transport to the closest port near the refinery; Final inland delivery and placement on its foundation.

This wasn’t a routine move. It tested our planning, adaptability, and calmness under pressure.

Heavy monsoon rains and foul weather pushed us to strengthen safety protocols; Tidal limitations at both ports demanded precise timing; MWS approvals needed thorough preparation and coordination; Road infrastructure challenges and ODC restrictions required route intelligence and careful execution.

And through it all, our teams ensured that every moment of the journey stayed safe and on schedule. Against the odds, the flash drum reached its destination smoothly, safely, and right on time.”

 
 

Total Movements, member to the Worldwide Project Consortium (WWPC) in India, moved a 311 ton weighting Water Flash Drum to one of the largest petroleum refineries in India – a task that demanded more than just logistics.

It required resilience, precision, and the collective spirit of everyone involved.

A spokesperson for the project team explained: “From the supplier’s factory to the refinery foundation, this drum travelled by road, by barge, and through challenging terrain.

Our scope covered: Road movement to the nearest jetty; Rolling the drum safely onto a barge; Coastal transport to the closest port near the refinery; Final inland delivery and placement on its foundation.

This wasn’t a routine move. It tested our planning, adaptability, and calmness under pressure.

Heavy monsoon rains and foul weather pushed us to strengthen safety protocols; Tidal limitations at both ports demanded precise timing; MWS approvals needed thorough preparation and coordination; Road infrastructure challenges and ODC restrictions required route intelligence and careful execution.

And through it all, our teams ensured that every moment of the journey stayed safe and on schedule. Against the odds, the flash drum reached its destination smoothly, safely, and right on time.”

 
 